Dampier Port Upgrade Phase A & B

 

Customer: Hamersley Iron (Rio Tinto)

Contract type:  Construct only

Location: Dampier, Western Australia 

 

 

Resources Solutions Ports & Coastal Solutions Australia

Fast Facts 

  • Two phase wharf upgrade
  • 600 m overall wharf extension
  • Extensive use of large scale modularisation
  • Work successfully completed within operating port without distruption

We delivered a major wharf upgrade in two phases for Rio Tinto at Dampier Port, using modularisation to accelerate construction and reduce the cost of onsite labour

Phase A included the construction of a 455 m wharf extension, a new access jetty, tail end structure, electrical deck, and modifications to the existing wharf.

Scope included 18 new dolphins, installation of new materials-handling infrastructure, including a 1,095 m conveyor system, transfer tower, and drive and take up structures. The precast deck modules were transported and lifted into place by heavy lift vessel.

Phase B was a 145 m extension of the wharf, and included installation of new conveyors and materials handling system.

The construction involved a shutdown for the removal and replacement of 220 m of conveyor in three weeks. There were upgrades of an additional 875 m of existing ore conveyors, new deck sleepers to the existing wharf, and strengthening under the shiploader.

Our team was able to achieve exceptional results within tough conditions. We were working within the confines of a fully operational wharf facility, which required close collaboration and constant communication between all associated parties. This also included coordination of multiple contractors undertaking works concurrently (marine, structural, electrical and mechanical).

Innovative in-house designed jack-up piling templates minimised downtime from inclement weather. 

We achieved project completion on time, with construction activities being undertaken in tight shutdown windows so as not to disrupt port operations.

Project Gallery