We've worked all over the airport, both landside and airside, completing a variety of upgrades, and the map below shows the footprint of our projects

Customer: Auckland International Airport Ltd
Contract type: Various
Location: Auckland, New Zealand
We've been working with the Auckland International Airport team since January 2019 to maintain and improve critical assets, including upgrading live jet fuel pipelines, renewing runway pavements, and much more.
We have also worked on vertical construction projects, including the new airport upgrade with subsidiary Built Environs.
We have installed fuel pipelines and utilities underground, relocated secure facilities, and built new roads and pavements - civil, mechanical, fabrication, pipelines, and vertical construction - we can do it all.
The projects listed below demonstrate how flexible and responsive we are to our clients’ needs. Just click on each project to find out more
The projects we have completed at the airport over the last six years include...
We've worked all over the airport, both landside and airside, completing a variety of upgrades, and the map below shows the footprint of our projects

Click on the boxes below to expand (and hide) them for more information about the projects, including detailed scope and delivery.
{slider title="
" open="false"}
The scope of work for all three stages included:
Civil works:
Mechanical Works:
Located on a live airfield, well-planned logistics and avoiding disruption to airport operations were critical.
We learned valuable lessons in this complex operational environment that we continue to apply and build on today, including:
{slider title="
" open="false"}
The project scope includes the construction of:
Project Awards:
The project made the finalists of the CCNZ Hirepool Construction Excellence Awards 2023, inr Category 4 - Projects between $20m and $100m.
{slider title="
" open="false"}
McConnell Dowell began the demolition of the existing parking areas and the construction of a new trucking route in February 2023.
The scope of work includes:
Construction of 5300m2 flexible and rigid pavement, new traffic barriers, islands, fencing, gates, footpaths and road furniture.
{slider title= "
" open="false"}
MCD was awarded the contract for Ring Main 4 – Phase 1 by AIAL in March 2023, and the work was completed in September 2023. This pipeline extension was part of the airport's fuel network growth and resilience programme. The new fuel main alignment crossed the airfield; excellent logistics and communications were instrumental in the project's success.
Civil works
Mechanical Works:
{slider title= "
" open="false"}
The project was awarded in July 2023 and completed in June 2024. The scope involved installing drainage infrastructure in Areas 4 A and B at the western end of the runway.
The work scope involved removing the first 200mm of topsoil and installing collector pipes east to west. Megaflo 170 sub-soil drains will be installed in Areas A and B and connected to the central collector pipe.
Once the infrastructure is installed, a Polydrain Geocomposite Membrane will be placed, covered with GAP65, and finally covered with topsoil and the grass reinstated.
{slider title= "
" open="false"}
We are completing some of the Taxiway Mike/Remote Stand Stage Two scope of the project for the main contractor, Brian Perry Civil, contracted by AIAL behind Pier B of the International Terminal.
The scope MCD is delivering is for the fuel line upgrades and includes, but is not limited to:
The project’s high-level objectives are to construct the airfield pavement for the Taxiway Mike and Lima Extension and Remote Stands Stage 2, including the installation of in-ground services, a new biofilter stormwater pond and a new Power Centre.
{slider title= "
" open="false"}
Taxiway Lima included two construct-only contracts to strip wrapping and costings from a pipeline and lay 100 metres of new fuel line in preparation for future airfield expansion.
{slider title= "
" open="false"}
The Pit 5 project is being completed on the Aviation Fuel Hydrant System (FHS) for Auckland International Airport Limited (AIAL). The project is the final scope of the Fuel Network Compliance programme, following the Terminal Development Project (TDP), the Fuel Diversion (FD), and the Fuel Network Compliance Stage 3 & 4 (FNCS 3 & 4) projects. The Pit 5 project scope includes replacing two adjacent Pits 5 & 14 at Aircraft Stand 7 and two hydrants (7A & 7B).
{slider title= "
" open="false"}
Find out more about this project on our Built Environs website here.
{/sliders}