Breakwater Road Realignment

Customer: VicRoads 

Contract type:  Construct only

Location: Geelong, Victoria

 

Fast Facts

  • 453 precast box culverts
  • 146 precast bridge beams
  • 10,600 cubic metres of concrete
  • 1,240 tonnes of steel
  • 50,000 cubic metres of earth fill material
  • 2,885 piles installed

McConnell Dowell successfully delivered the Breakwater Road Redevelopment project in Geelong. The realignment of the road was undertaken to ensure improved and safer transport links, in what is one of Victoria’s fastest growing areas and a primary growth corridor for future urban development in Greater Geelong.

Breakwater Road is an essential crossing of the Barwon River, carrying around 20,000 vehicles each day. The existing bridge was in a flood plain and when it rained heavily it was closed down, forcing traffic through the centre of Geelong and causing delays for drivers. There was also a height restriction with the exiting intersection which meant trucks bigger than 3.7 metres couldn't fit under the Melbourne-Warrnambool rail bridge.

McConnell Dowell's scope of work included:

  • Realignment of approximately 1.1 km of Breakwater Rd including a 654m x 14m wide bridge; including one span over railway tracks, and another a 60m span over Barwon River
  • Box culvert crossing
  • Reinforced Earth walls
  • Tie-in roadworks at each end
  • Lighting & Traffic Signals.

Innovations & Savings

Despite it being a construct only contract, McConnell Dowell recognised the geotechical challenges the flood prone area would present. So the company undertook a full cost-benefit analysis of all potential ground improvement options during the tender, to mitigate potential risks and find possible cost savings. 

Based on this analysis McConnell Dowell offered an alternative solution based on CMC (Controlled Modulus Columns), the original tender design was for CSM (Cutter Soil Mixture). This provided the most effective solution for the given conditions.

Savings of over $100,000 were achieved, compared with the original design approach, as was a time savings of 57 days (compared with the original tender program using CSM, which would have taken 97 days).

Completed on time and within budget, the new bridge was built 12 metres higher than the existing bridge, meaning Breakwater Road will now be able to withstand a one in 20 year flood as well as allow for bigger trucks, reducing the number of trucks going through Geelong.

 

Project Gallery