Procurement Packages for 250MW Kidston Pumped Storage Hydro Project

MCD MH JV

 

 

 

McConnell Dowell Constructors (Aust) Pty Ltd and John Holland Pty Ltd  in joint venture (MDJH JV) have been engaged by Kidston Hydro Project Co ATF the Kidston Hydro Project Trust as the EPC Contractor for the 250MW Kidston Hydro Pumped Storage Project.  The Project is located 270km NW of Townsville and utilises the abandoned Kidston Gold Mine as the foundation for the Project, with the mining pits acting as the upper and lower reservoirs. 

This Project received funding from ARENA as part of ARENA’s Advancing Renewables Program

 

Note:

  • The below list is an estimate of potential packages, for reference only, for the project
  • Supplier's wishing to submit Expressions of Interest (EOI) are to email This email address is being protected from spambots. You need JavaScript enabled to view it. with capability statement and areas of interest in the Project (this is a monitored email address).
  • Date(s) indicated below may change and this is only for information purposes.
  • MDJH JV will screen and select suppliers based on local industry requirements / specialisation and capability to perform work as required
  • Registration on Felix does not mean you will be shortlisted for any packages but is a mandatory requirement for any Suppliers invited to RFQ's
  • To be listed on the MDJH JV system, pre-qualification for registration to be done via https://mcconnelldowell.okfelix.com/panel_registration/registered_vendors
  • The project is D&C and will run over 3+ years so packages will come to market over a period of time.
  • Packages will be awarded both on price / non price factors.

 

Pkg No.  Package Description  Notes  Status RFQ release Date
PK001a Survey - Early Works Awarded to Minstaff Survey Awarded Completed
PK001b Survey - Permanent Works  Awarded to Minstaff Survey Awarded Completed
PK002a SE - Site Offices & Ammenities Awarded to ATCO Awarded Completed
PK002b SE - Dome Shelters Awarded to Container Domes Australia Awarded Completed
PK003 SE - Power & Services Awarded to PBE Rutherford Awarded Completed
PK004 SE - Fencing  RFQ to be released around 30/1/24 Not Started T.B.A
PK005 Concrete Supply  Awarded to Holcim Awarded Completed
PK006 FRP RFQ to be released around 31/3/22 Not Started T.B.A
PK006a FRP - Tunnels RFQ to be released around 21/11/22 Not Started T.B.A.
PK007a Reinforcement of Eldridge Pit Awarded to Geovert In Progress Completed
PK007b Reinforcement Supply RFQ to be released around 31/10/21 Not Started T.B.A
PK007c Rockbolt Supply Pending RFQ responses  In Progress 10/8/21
PK008a Labour Hire - Indigenous  Awarded to ATW In Progress Completed
PK008b Labour Hire - General RFQ to be released around 31/10/21 Not Started T.B.A
PK009 Blank   Not Started T.B.A
PK010 Fuel Supply Awarded to Maranos Fuel In Progress Completed
PK011 Site Security systems / Other?   Not Started T.B.A
PK012 Waste Management   Not Started T.B.A
PK013 Consutants Noise & Vibration etc, TWD, Community Stakeholder, Heritage / Indigenous? Not Started T.B.A
PK014 Quarry Supply   Not Started T.B.A
PK015a Structural Steel Supply RFQ to be released around 15/2/22 Not Started T.B.A
PK015b Escape Stair Towers Fabrication RFQ to be released around 20/12/22 Not Started T.B.A
PK015c Tunnel Lining (tubular) RFQ to be released around 3/3/22 Not Started T.B.A
PK015d Tunnel Steel Liners RFQ to be released around 26/12/22  Not Started T.B.A
PK016 Crane Hire   Not Started T.B.A
PK017 Plant Hire   Not Started T.B.A
PK017a Concrete Pumping RFQ to be released around 2/6/22  Not Started T.B.A
PK017b Plant Maintenance and Repair   Not Started T.B.A
PK017c SiteVehicles Awarded to Southside Toyota / Entire Fleet Solutions In Progress Completed
PK017d Plant hire - Dam Embankments Schedule of rates agreement with; MAAS, Egans, Dundrum, SU Tunnel & Civil, Greenacres Group, Bolwarra Enterprises In Progress Completed
PK017e Plant hire - Tunnels & SMP   Not Started T.B.A
PK018 Crash Barriers Supply RFQ to be released around 16/8/21  Not Started T.B.A
PK019 Signage   Not Started T.B.A
PK020a HDPE Liner - Consulting Awarded to Fabtech Awarded Completed
PK020b HDPE Liner Supply   Not Started T.B.A
PK021 Lift Supply To be determined as per the design development - current design does not include a lift for the shafts or the powerhouse. To be assessed by Mid-2022 Not Started T.B.A
PK022a Overhead Crane - Flap Gate Area Cancelled Cancelled Cancelled
PK022b Overhead Crane - Surface Workshop Cancelled Cancelled Cancelled
PK022c Overhead Crane - Construction in Cavern RFQ to be released around 20/1/22  Not Started T.B.A
PK022d Overhead Crane - Main Cavern RFQ to be released around 20/1/22 Not Started T.B.A
PK023 Earthworks Packages RFQ to be released around 26/1/22 Not Started T.B.A
PK023a Dam Construction (inc Fuel) RFQ to be released around 26/1/22 Not Started T.B.A
PK023b Dam Embankments RFQ to be released around 26/1/22 Not Started T.B.A
PK023c Surface Blasting RFQ to be released around 4/2/22  Not Started T.B.A
PK023d Acces Roads RFQ to be released around 25/5/21 Not Started T.B.A
PK023e Dam Spillway Penstock RFQ to be released around 7/2/22 Not Started T.B.A
PK024 Earthwork Consumables   Not Started T.B.A
PK024a Explosive Supply Awarded to JonEx In Progress Completed
PK025 Tunneling Packages Cancelled as to be self performed by MDJH JV Cancelled Cancelled
PK025a Raise boring shaft  RFQ released In Progress 28/6/21
PK025b Long hole drilling RFQ to be released around 2/8/22  Not Started T.B.A
PK025c Tunnel Sealing   Not Started T.B.A
PK025d Geotechnical Investigation Drilling Awarded to Mulligans Geotechnical Completed Completed
PK026 E&I Packages RFQ's to be released around 18/10/22 Not Started T.B.A
PK026a CCTV - Permanent package RFQ to be released around 12/3/24 Not Started T.B.A
PK026b BOP / SCADA Controls RFQ to be released around 18/10/22 Not Started T.B.A
PK026c Data / Comms RFQ to be released around 29/12/22 Not Started T.B.A
PK026d Surface HV/LV Substation works, cabling RFQ to be released around 24/10/22 Not Started T.B.A
PK027 E&I Consumables   Not Started T.B.A
PK027a Power, Instruments and Controls RFQ to be released around 28/9/21 Not Started T.B.A
PK027b Cable Support Systems RFQ to be released around 28/9/21 Not Started T.B.A
PK027c Power Cables RFQ to be released around 16/8/22 Not Started T.B.A
PK027c Lights and Fittings RFQ to be released around 28/9/21 Not Started T.B.A
PK028 Mechanical Packages RFQ to be released around 20/12/22 Not Started T.B.A
PK029 Mechanical Consumables RFQ to be released around 20/12/22 Not Started T.B.A
PK030 HVAC Packages RFQ to be released around 21/6/21 Not Started T.B.A
PK030a Ventiliation and HVAC RFQ to be released around 21/6/21 Not Started T.B.A
PK031 HVAC Consumables RFQ to be released around 21/6/21 Not Started T.B.A
PK032a OEM Hydro Plant Awarded to Andritz Awarded Completed
PK032b Trash Racks RFQ to be released around 7/12/23 Not Started T.B.A
PK032c Oil Water Separator   Not Started T.B.A
PK033 Fire Detection / Protection Systems RFQ to be released around 7/10/23  Not Started T.B.A
PK034 Powerhouse Packages   Not Started T.B.A
PK034a Powerhouse Ventilation RFQ to be released around 28/7/23  Not Started T.B.A
PK034b Powerhouse Goods / Personnel Lift Cancelled Cancelled Cancelled
PK035 Construction Lift Cancelled  Cancelled Cancelled
PK036a Freight Forwarding and Logistics To be reviewed as/when required and limited to MCD panel providers  Not Started T.B.A
PK036b Heavy Transport and Skate   Not Started T.B.A
PK037 Field Lab Testing   Not Started T.B.A
PK038 Charter Flights Awarded to AVMIN In Progress Completed
PK039 Building Permanent Awarded to ATCO Completed Completed
PK040 Firewater Tanks RFQ to be released around 17/10/23 Not Started T.B.A
PK041 Diesel Generators   Not Started T.B.A
PK042 O&M Services Cancelled Cancelled Cancelled
PK043 Dewatering Awarded to Schlumberger In Progress 4/6/21
PK044 Blank   Not Started T.B.A
PK045 Precast RFQ to be released around 29/9/22 Not Started T.B.A
PK046 Formwork D&S RFQ to be released around 29/3/22 Not Started T.B.A
PK047a Sewer Pumping Equipment   Not Started T.B.A
PK047b Sewer Disposal System (Oxi Clean)   Not Started T.B.A
PK048 Auxillary Transformers  RFQ to be released around 20/6/22 Not Started T.B.A
PK049 PPE and other consumables  Awarded to Blackwoods In Progress Completed