Client National Environmental Agency
Location Singapore
Contract Design and Build
Completion December 2018

Project Capabilities

Roads & Bridges

Fast Facts

  • Route 2 Bridge - Vehicular Road Bridge, 500m long
  • Route 3 Bridge – Vehicular Road Bridge 750m long
  • Marine Deck 450m long at Tuas View Basin

Project Summary

The design and build of two road access bridge at Tuas Basin to serve an up and coming NEA and PUB integrated Waste Management Facility (IWMF) and Tuas Water Reclamation Plant (TWRP) will be constructed in the future.   

Two road bridges over the intake canal of Tuas Power Station

  • Route 2 Bridge - Vehicular Road Bridge, 500m long
  • Route 3 Bridge – Vehicular Road Bridge 750m long
  • Marine Deck 450m long at Tuas View Basin
  • Ground Improvement works -1.8million m3 of Ground improvement works on the Tuas View Basin facilitating the Bridge Construction
  • Roadworks

Challenge

Constructing the bridge over Tuas Power Generation’s intake canal without encroaching into their area. To achieve this a bridge, with a 70-meter-long span to was designed, one of the longest single spans in Singapore.

Constructing 7 nos 50-meter-long U-Beams each weighing 270 tonnes at MCD’s own pre-cast yard and transporting them to site.

Space constraint, it has been essential to relook at the designs and define the heavy lifting criteria to mitigate high risk activities. 

Project Gallery