Introduction General

Introduction General

Thank you for the opportunity to present this brief capability statement which details a cross-section of our skills and experience, and showcases a selection of our recent projects.

About Us (typically use first)

About Us (typically use first)

For over 65 years customers have been coming to McConnell Dowell with complex projects that require innovative solutions. That's why we're known as the Creative Construction company.

From remote resources and energy projects to city-shaping infrastructure, we've built thousands of quality assets and facilities.

Engineering-led, our expertise has grown steadily to span building, civil, electrical, fabrication, marine, mechanical, pipelines, rail, tunnel and underground construction..

Our Approach (typically use 2nd or 3rd)

Our Approach (typically use 2nd or 3rd)

We approach every project with a focus on creativity and certainty - seeking the right blend of innovation and safe, proven approaches so we can exceed our customers' expectations.

We also understand that construction today is as much about community and sustainability as it is about concrete and steel. Our unwavering objective and commitment is to deliver what we promise to our customers, while protecting and enhancing our people, the community and the environment.

Oil & Gas

Oil & Gas

From major processing facilities to marine infrastructure we've have been delivering creative solutions to the international oil and gas industry for more than 50 years.

Our fully-integrated service includes civil works, marine and cross-county pipeline construction, fabrication and structural mechanical piping (SMP) - all supported by our global engineering and procurement capabilities.

Our construction and commissioning schedules are coordinated locally to take advantage of a strong understanding of regional construction capabilities, capacity and performance. This enables us to control safety, quality, scheduling and costs.

Jemena Early Contractor Involvement Northern Territory & Queensland, Australia

Northern Gas Pipeline

Constructing a 481 km transmission pipeline providing gas reserves to industries in Mt Isa

Engaged by Jemena under an exclusive ECI agreement, we designed and constructed the remote Northern Gas Pipeline, opening up the Northern Territory's gas reserves to industries in Mt Isa, Queensland.

Our scope involved the design and construction of approximately 481 km of 12-inch diameter high pressure gas transmission pipeline and associated pipeline facilities including two mainline valves and a midline scraper station. The pipeline transports gas from existing offshore and onshore gas reserves in the Northern Territory and will supply this gas to Incitec Pivot’s Phosphate Hill plant located south of Mt Isa and other users.

Fast Facts

  • 481 km, 12 inch pipeline
  • Three cathodic protection stations
  • Three mainline valve stattions
  • One midline station (pig trap)
Northern Gas Pipeline
APA Group Construct Only Western Australia

Lake Way and Karlawinda Gas Pipelines

We constructed the Lake Way Gas Pipeline (LWP) and the Karlawinda Gas Pipeline (KGP) projects for APA Group in Western Australia.

The LWP pipeline is located 15 kilometres south of Wiluna and transports natural gas from APA’s Goldfields Gas Pipeline (GGP) to SO4’s Lake Way facility. SO4 aims to become a major exporter of Sulphate of Potash and the LWP pipeline provides gas for fuelling power generating facilities and other equipment within their process plant.

Fast Facts

  • Two high pressure gas pipeline projects
  • 26 km of DN100 gas pipeline
  • 56 km of DN100 gas pipeline
Lake Way and Karlawinda Gas Pipelines
APA Group Construct Only Lenora, Western Australia

Murrin Murrin Gas Pipeline Looping

We constructed the Murrin Murrin Looping Project for APA Group, east of Lenora in Western Australia. The objective of the project was to increase the capacity of the Murrin Murrin Lateral to enable APA to service future downstream customers.

Our scope consisted of the construction of a 13.8 km long, 200 mm diameter high pressure gas pipeline, along with the tie-ins to an existing above-ground offtake station. The pipeline runs from a connection off the existing Murrin Murrin Lateral.

Fast Facts

  • 13.8 km, 200 mm diameter gas pipeline
  • Zero Lost Time Injuries
  • Practical completion acheived 3 days early
Murrin Murrin Gas Pipeline Looping
  APA Group Construct Only Leinster, Western Australia

Agnew Gas Pipeline

After extensive pre-planning and a fast mobilisation, we constructed the Agnew Gas Pipeline Project for APA Group in the south-southwest of Western Australia. The new pipeline supplies gas to the Agnew gold mine site to supplement the mine’s renewables-fuelled power supply.

Our scope consisted of the construction of a 25 km long, DN150 mm, dual layer FBE coated, AS2885 compliant, high pressure natural gas pipeline, along with the tie-ins to the swan necks at the above ground Kyarra Offtake Station and the Agnew Delivery Station.

Fast Facts

  • 25 km long, 150 mm diameter gas pipeline
  • Multiple horizontal directional drills (HDDs) under roads
  • Fast mobilisation
  • Computerised radiography used
Agnew Gas Pipeline
Australia Pacific LNG EPC Gladstone, Queensland

APLNG Pipeline

Following successful completion of an Early Works contract for the APLNG project, MCJV, a joint venture between ourselves and Consolidated Contracting Company Australia Pty Ltd, was awarded an EPC contract for delivery of 360 km of the main export pipeline, a 57 km lateral pipeline, and associated facilties.

The overall APLNG project included the development of substantial coal seam gas resources in the Surat and Bowen Basins. The key elements of the project were the transmission pipeline, subsea crossing (Narrows Crossing) and a multi-train LNG facility on Curtis Island, near Gladstone.

Fast Facts

  • 360 km, 42" mainline pipeline
  • 57 km, 36" lateral pipeline
  • Launcher station at Condabri
  • Pipeline hub
  • Midline scraper station
  • 4 mainline valve stations
APLNG Pipeline
QCLNG Pipelines EPC Curtis Island, Queensland

Narrows Crossing (QCLNG)

In joint venture with Consolidated Contracting Company (the MCJV), we designed and delivered the Narrows Crossing project, one of the most diverse and challenging pipeline projects ever completed in Australia.

Our scope involved the connection of the QCLNG and APLNG 42” export pipelines from their termination points across the Narrows Channel to the LNG plant on Curtis Island. We also delivered the QCLNG Delivery Station.

Fast Facts

  • 12 km, 42 inch twin pipelines
  • Two 8 inch FOC ducts
  • 1.5 km HDD Crossing
  • 2.3 km marine pipe pull
  • Restricted right of way
  • Extensive environmental controls
Narrows Crossing (QCLNG)
Fluor Australia Pty Ltd Construct Only Roma, Queensland

GLNG Upstream - Roma Hub and Pipelines

We constructed a 145 TJ per day gas compression and water treatment hub, with associated infrastructure and water gathering lines, at the coal seam gas fields north east of Roma in Queensland. The infrastructure enabled collection and processing of gas for delivery via an export pipeline to an LNG processing plant on Curtis Island, off Gladstone.

The large and complex project required a multi-disciplinary approach, with a focus on facilities for gas compression, power generation and water treatment, in addition to pipeline construction.

Fast Facts

  • 287 km, 63-800 mm diameter PE pipelines
  • 40 km, 100-250 mm diameter CS pipelines
  • LTI free
GLNG Upstream - Roma Hub and Pipelines
ExxonMobil EPC Jurong Island, Singapore

VTB Subsea Pipeline Jurong Island

We joint ventured with ITP (IMJV) to design and construct the VTB (Vacuum Tower Bottoms) Subsea Pipeline for ExxonMobil in Jurong Island, Singapore.

Vacuum Tower Bottoms are the left over bottom product of distillation, which can be processed in cokers and used for upgrading into gasoline, diesel and gas oil.

Fast Facts

  • 2 km long, 12 inch dia. subsea pipeline
  • Pipeline heated to 200 degree celcius
  • Shore crossings
VTB Subsea Pipeline Jurong Island
PTT Public Company Limited Construct only Rayong, Thailand

Fourth Transmission Pipeline Phase 2 (FTP2)

The FTP2 Project was awarded to our Thailand team and involved approximately 70 km of 42" high-pressure gas pipeline constructed between Rayong LNG Terminal in the south to the Wang Noi – Kaeng Khoi Pipeline Tie-in Station in the north.

Work was spread over 300 km and involved more than 20 km of trenchless pipe installation and construction of significant above-ground facilities. The peak site workforce exceeded 2,800 across 50 discrete work locations.

Fast Facts

  • 70 km of 42" X70 High Pressure gas pipeline
  • 3 km Thrust Bores
  • 20 km of Horizontal directional drills and direct pipe installation
  • Over 4 million hours worked LTI free
Fourth Transmission Pipeline Phase 2 (FTP2)
Safety

Safety

We never compromise on safety.

We foster our 'Home Without Harm' safety culture through robust processes, effective systems, and by recognising and rewarding safe behaviours.

Our Site Safety Managers are always on our project leadership teams, ensuring safety is prioritised in all site activities. Every team member has clear safety responsibilities, aimed at protecting themselves, their colleagues, and the community.

We're also leading our industry in the adoption of new safety technologies, like virtual reality plant simulators and AI-enabled blind spot elimination. Check out the case studies below for more information.

Underpinning it all are our Safety Golden Rules. Built on our long-term collective knowledge and learnings, they are specifically targeted at preventing fatalities and serious injuries.

inpage image safety

SGR webpage banner

safesites banner wide

Sustainability (ESG)

Sustainability (ESG)

Our purpose is 'Providing a Better Life’ - today and into the future. That’s why sustainability, in all its forms, is considered in every project, process and product across our business.

Our approach is clearly articulated in our Sustainability Policy.

We're about action not just aspiration. Our ambitious but achievable {tip title="Carbon Reduction Roadmap" content="MCD Carbon roadmap 2030"} carbon reduction road-map {/tip} will see us be operationally net zero by 2030, with 44 initiatives that are being progressively rolled out across the company. Last year we reduced our carbon emissions by 442 tonnes through the use of solar technologies alone, and diverted almost two million tonnes of waste from landfill.

Digital Engineering

Digital Engineering

We take a ‘Digital First’ approach to all our projects, equipping our teams with the latest digital tools and systems from the design stage forward.

This helps them identify and address potential issues at the earliest stages of project development, effectively eliminating issues at their genesis leading to lower costs and delays once we start on site.

On site, we use digital tools like drones for surveying, and GPS tracked plant to monitor and improve safety and efficiency.

Closing Text - General, with video, no contacts

Summary

Thank you for taking an interest in McConnell Dowell's skills, capabilities and approach. Additional information is available on our website, including additional project case studies.

Contacts

Peta Wilkes

Peta Wilkes

Pre-Contracts Manager - Qld & NT

LinkedIn
Leon Richards

Leon Richards

Group Technical Director - Resources

LinkedIn