Capability Statement

Capability Statement

Prepared for Palmerston North City Council

May 2026

NZP Intro (typically use 4th to 8th)

NZP Intro (typically use 4th to 8th)

With over 65 years of history in the region, and as the birthplace of the company, McConnell Dowell is well known in New Zealand and the Pacific Islands as an accomplished, engineering-led, multi-disciplined contractor.

We have a proven track record in delivering complex projects in remote and difficult locations, and have extensive in-house resources, specialist plant, and experienced support teams that enables us to self-perform much of our work.

Water & Wastewater Solutions

Water & Wastewater Solutions

We understand what matters most to our water industry customers - uninterrupted supply, minimal disruption, safety, compliance, and positive community engagement.

We've been entrusted with the design and delivery of major metro desalination and water treatment plants, as well as the construction of dams and large-diameter pipeline and pump station networks.

We've delivered approximately $9 billion in new water assets over the last 15 years, including:


Wellington Water Construct Wellington, New Zealand

Barber Grove to Seaview Wastewater Treatment Plant Pipe Duplication

Future proofing and improving water quality

We used the optimum mix of tunnelling and trenched construction techniques to deliver the Barber Grove to Seaview Wastewater Treatment Plant Pipe Duplication Project for Wellington Water, causing the least impact possible.

The project involved the installation of a new 1.2 km long, 1 m diameter pressurised wastewater pipeline. It services 90% of the residents in Hutt Valley, improving water quality and catering to the region’s growth.

Fast Facts

  • 1.2 km long, 1 m dia. pressurised wastewater pipeline installed up 9 m deep
  • 55% of the alignment installed using micro-tunnelling
  • 4 No. shafts for access tunnel
Barber Grove to Seaview Wastewater Treatment Plant Pipe Duplication
Gisborne District Council Construct Gisborne, New Zealand

Gisborne Wastewater Treatment Plant Upgrade – Stages One & Two

In Gisborne, on the east coast of New Zealand’s North Island, we upgraded a wastewater treatment plant, doubling its existing capacity while saving our customer 30% in construction costs.

The budget for the Gisborne Wastewater Treatment Plant Upgrade – Stages One & Two was tight, but we love a value-engineering challenge! Working with the Gisborne District Council, the team rescoped and redesigned the construction method, reducing the cost by 30% and reducing the carbon footprint of the job.

Fast Facts

  • 8500 m3 material stabilised, forming a 5 m deep 'earth raft'
  • 12 m deep steel piled temporary cofferdam
  • 6 m deep permanent pump station
  • 2 No. 11 tonne tanks
  • 9 m high stainless-steel tank
Gisborne Wastewater Treatment Plant Upgrade – Stages One & Two
Watercare Services Ltd type:Construct only Auckland, New Zealand

Māngere Biological Nutrient Removal Facility Upgrade

Expanding wastewater treatment capacity to meet growing demand

In joint venture, we delivered an additional Biological Nutrient Removal (BNR) facility for Watercare, streamlining the programme and providing alternate solutions that reduced the cost of this complex brownfield project. The facilty provides additional secondary treatment capacity for approximately 250,000 people.

The project, which was part of Watercare's expansion of their Māngere Resource Recovery Facility (MRRF) in Auckland, won a IPWEA 'Best Public Works Project' award.

Fast Facts

  • 200 staff
  • 830,000-man hours worked
  • 120,000 m3 earth moved
  • 15,500 m3 of concrete poured, or 750 concrete truckloads
  • 2,400 No. 150 mm steel piles each weighing 500 kg
  • 323 No. precast concrete panels
Māngere Biological Nutrient Removal Facility Upgrade
Watercare Services Ltd Construct only Auckland, New Zealand

Digester 8 Upgrade

The Digester 8 Tank is one of eight mesophilic anaerobic digester tanks at the plant where wastewater is stored. Bacteria break down the organic matter inside this pressure vessel as part of the wastewater treatment process. The project's scope of work includes:

The aim is to improve and extend the digester's working life, which, when regularly maintained, can last up to 50 years.

Fast Facts

  • Refurbishment of Digester 8
  • one of eight mesophilic anaerobic tanks at the plant
  • advanced management and maintenance techniques deployed
Digester 8 Upgrade
Watercare Services Ltd Construct Only Auckland, New Zealand

Pukekohe Wastewater Treatment Plant Upgrade

Value-engineered, fast-tracked upgrade

We delivered this state-of-the-art wastewater treatment plant upgrade in Auckland, drawing on our learnings from past projects to value-engineer the design and fast-track the programme. We delivered the project on time and within budget, all while keeping the existing plant fully operational.

We were engaged (in joint venture) by Watercare to upgrade the Pukekohe Wastewater Treatment Plant to support population growth in Franklin, and improve the quality of the water discharged into the Waikato River.

Fast Facts

  • 3,950 m3 of concrete insitu
  • 447 tonnes of steel reinforcing
  • 404 precast concrete panels and beams
  • 4,120 m of underground pipework
  • 7,820 m of stainless-steel pipework above ground
  • 106,680 m of cabling including power, communication and instrument
Pukekohe Wastewater Treatment Plant Upgrade
Watercare Services Ltd Construct Queen Street, Auckland

Queen Street Wastewater Diversion Project

For the first time in New Zealand, a Direct Pipe® micro-Tunnel Boring Machine (mTBM) and traditional pipe jacking methods were used to install Glass Reinforced Plastic (GRP) pipes in a single drive.

We utilised two different tunnelling systems, doubling down on innovation to install a new pipeline for the Queen Street Wastewater Diversion Project in Auckland, New Zealand. On the project, we managed the tunnelling scope for lead contractor Fulton Hogan and client Watercare to construct a 570-metre-long wastewater pipeline in the city centre under Queen Street.

Fast Facts

  • a new 570-metre-long wastewater pipeline
  • 1229 mm diameter, 5.8 m long sections of Glass Reinforced Plastic Pipe (GRP)
  • Installed between three shafts, in a continuous drive
  • 353 m from Mayoral Drive to Wellesley Street
  • and 217 m from Wellesley to Victoria streets
  • up to 14 metres below Queen Street
Queen Street Wastewater Diversion Project
Queenstown Lakes District Council Construct only Queenstown, South Island, New Zealand

Shotover Wastewater Treatment Plant Upgrade

Improving environmental outcomes and facilitating future growth for communities

Protecting the environment and minimising disruption to existing operations were key to securing the second stage of the Shotover Wastewater Treatment Plant Upgrade in picturesque Queenstown.

Our project was the third (and final stage) of Queenstown Lakes District Council’s 20-year-long programme to transition the plant from the traditional Biological and Aerated Pond Treatment processes to the more effective and efficient ‘Activated Sludge Treatment’ method.

Fast Facts

  • Reused 10,000 m3 of spoil in a temporary bund for land reclamation
  • Constructed 11,000 m3 engineered gravel raft
  • Safely repurposed 1100 dry tonnes of sludge
  • Built new 34 m diameter Clarifier
  • and 24 m x 80 m x 6.2 m MLE Reactor Tank
  • Decommission an oxidation pond
Shotover Wastewater Treatment Plant Upgrade
Watercare Services Ltd Design and Construct Mahurangi East, Auckland

Snells Algies Wastewater Pipe & Outfall

Improving wastewater infrastructure while minimising disruption

Proposing a trenchless solution to minimise disruption, Watercare Services awarded us the Snells Algies wastewater pipe and outfall construction project. It resulted in new world record - a 2021 metre long Direct Pipe® drive delivered using a micro tunnel boring machine.

The project was the first phase of a three-phased scheme to improve water quality in the Mahurangi Harbour and cater for population growth in the Warkworth and Mahurangi East communities north of Auckland.

Fast Facts

  • 2021 m world record Direct Pipe® drive by MTBM
  • 4.3 km of 630 mm diameter HDPE pressure/gravity main installed in open trench
  • 2 km of 1.2 m diameter steel pipe installed using the Direct Pipe® system
  • 230 m outfall pipeline
  • 530 m of 710 mm diameter HDPE pipe using horizontal directional drilling (HDD)
  • 1220 mm OD steel pipe for the Direct Pipe®, 32 mm wall thickness
Snells Algies Wastewater Pipe & Outfall
Auckland Council Healthy Waters Construct St Marys Bay, Auckland

St Marys Bay Water Quality Improvement Project

Improve water infrastructure to address water quality issues near Auckland

Limiting our construction footprint was a key part of our delivery approach for the St Marys Bay Area Water Quality Improvement Project in Auckland.

Now complete, this Auckland Council Healthy Waters project reduces the frequency of releases of stormwater overflow into the Waitematā Harbour by 95%. It provides storage in the form of a 1.8 m diameter, 2 km long underground pipeline, and a new 450 m long ocean outfall. Stored water is pumped back into the sewer network when there is capacity. Discharged water is released far away from places where people swim.

Fast Facts

  • 2 2 km long, 1.8 m diameter storage pipeline installed 18 - 25 m below buildings
  • 450 m ocean outfall
  • A new pumping and screening station and odour control unit
  • Three shafts for entrance and egress for the TBM
  • A new weir structure and odour control unit.
St Marys Bay Water Quality Improvement Project
Watercare Services Ltd Design & Construct Warkworth, Auckland

Warkworth Wastewater Pump Station

Improving Watercare's wastewater network

Using an innovative caisson (sunk shaft) construction method, we designed and delivered the Warkworth Pump Station, part of Watercare's broader scheme to improve the wastewater network from Warkworth to Snells Beach.

We built the new 247 litre per second wet-well / dry-well pump station adjacent to an existing pump station in Lucy Moore Memorial Park, implementing construction strategies and approaches to protect the sensitive park and river environment.

Fast Facts

  • 247 litres/sec pump station
  • Above and below-ground structures
  • Part of a broader wastewater scheme delivered by McConnell Dowell
Warkworth Wastewater Pump Station
Water & Wastewater Solutions

Water & Wastewater Solutions

We understand what matters most to our water industry customers - uninterrupted supply, minimal disruption, safety, compliance, and positive community engagement.

We've been entrusted with the design and delivery of major metro desalination and water treatment plants, as well as the construction of dams and large-diameter pipeline and pump station networks.

We've delivered approximately $9 billion in new water assets over the last 15 years, including:


Dunedin City Council Works panel Dunedin/Ōtepoti, New Zealand

Dunedin City Council

Sawyers Bay Renewals, Three Waters Framework Contract & Three Waters Renewals Programme

Through our local office, we've been working with Dunedin City Council to successfully deliver 'three waters' (wastewater, stormwater, and drinking water) upgrades.

As a member of the Council's works panel, we are one of a small number of organisations upgrading the city’s water and wastewater treatment plants through to 2031.

Fast Facts

  • $140 million of upgrades
  • 8 year long panel arrangement
  • 6 water treatment plants
  • 3 wastewater treatment plants
Dunedin City Council
Watercare Services Ltd Design & Construct Warkworth, Auckland, New Zealand

Warkworth to Snells Transfer Pipeline

Enhancing wastewater management for a sustainable future

Drawing on our industry-leading trenchless construction experience, we delivered the Warkworth to Snells Transfer Pipeline for Watercare, continuing our strong relationship with them.

The project was part of Watercare's North-East Wastewater Servicing Scheme, which conveyed wastewater from Warkworth to Snells Beach. The scheme will cater for future growth and enable Watercare to decommission the existing Warkworth Wastewater Treatment Plant, which discharges into the Mahurangi River.

Fast Facts

  • 1.4 km long dual rising main
  • 3.6 km long single gravity sewer
  • 409 steel pipes, each 1219 mm in diameter and weighing 6.85 tonnes
  • Water NZ Project of the Year 2025
Warkworth to Snells Transfer Pipeline

Closing Text - General with contacts, no video

Summary

Thank you for taking an interest in McConnell Dowell's skills, capabilities and approach. Additional information is available on our website, including additional project case studies.

Contact us through the link(s) below for advice or assistance with your project.

Contacts

Sven Harlos

Sven Harlos

Water Sector Lead<br>New Zealand & Pacific

+64 21 987 419

LinkedIn