Prepared for Prepared for RPS - Henderson Defence Precinct
May 2026
From remote resources and energy projects to city-shaping infrastructure, we've built thousands of quality assets and facilities.
Engineering-led, our expertise has grown steadily to span building, civil, electrical, fabrication, marine, mechanical, pipelines, rail, tunnel and underground construction..
We do that through delivering projects that connect, sustain and enhance communities, and through providing career opportunities that challenge, reward and grow our people.
We also have five company values that guide our behaviours and decisions. Our values are:
We also understand that construction today is as much about community and sustainability as it is about concrete and steel. Our unwavering objective and commitment is to deliver what we promise to our customers, while protecting and enhancing our people, the community and the environment.
From wharves and jetties to ocean outfalls, breakwaters, and submarine pipelines — we bring coastal confidence to every project.
Our modular approach to construction has helped create productive ports for clients like Rio Tinto, FMG, Vale, and BHP, where over 1.2 billion tonnes of iron ore are shipped annually from wharves we built.
We thrive in complex, operational environments — delivering innovative temporary works and safe, efficient methods that protect people, environment, and productivity. From purpose-built barges to proven marine systems, we engineer safe harbours with precision and care.
At McConnell Dowell, we don’t just build marine infrastructure — we deliver it with certainty, creativity, and a commitment to results.
We refined the initial concept design and constructed a new outer wharf structure at HMAS Coonawarra in Darwin to support the Australian Defence Force (ADF). The project involved the construction of a new 250 m long wharf and two approach jetties.
While the final structures are simple in their geometry and configuration, the site location and operational requirements were challenging.
In one of the first Early Contractor Involvement (ECI) contracts in Australia, we designed and delivered the Techport Australia Common User Facility - a new state-of-the-art shipbuilding and maintenance complex on the Port River at Osborne, South Australia. We delivered it in joint venture with our building company, Built Environs (the MDBE JV).
The project was rolled out in two stages. In the first stage, our team worked in collaboration with design and technology partners and DefenceSA to develop the final design and risk adjusted price.
We partnered with the Department for Infrastructure and Transport (DIT) to design and construct the new Granite Island Causeway Project. The awarding of the contract followed a collaborative design development process involving DIT, ourselves and our design consultant, WGA.
The Granite Island Causeway, located 83 kilometres south of Adelaide in Victor Harbor is a tourism, commercial and recreational landmark. It is the only link between Granite Island and Victor Harbor and is used by pedestrians, the iconic horse drawn tram service, a small number of vehicles that service the island, tourism attractions and the fishing industry. It is estimated that the number of pedestrians accessing the Causeway is approximately 700,000 per annum.
Engaged by Squadron Energy, one of Australia’s leading renewable energy companies, we helped establish a new gas import facility at Port Kembla to bring flexible additional energy supply to the eastern seaboard of Australia.
The facility, built on an abandoned coal export terminal, has the capacity to supply more than 70% of NSW’s gas needs.
We delivered the New Bridgewater Bridge project in Hobart - Tasmania's largest ever transport infrastructure project and one of the longest road bridges over water in Australia. The Tasmanian Department of State Growth awarded us the contract based on our innovative design and focus on local industry participation.
The new 1.28 kilometre long bridge replaces the existing lift-span bridge built in the 1940s, providing a new modern crossing of the River Derwent. The new bridge will cut travel times for the 22,000 people that use the route each day. It will also improve freight movement around the state capital.
We recently completed Stage 1 of the Swanson Dock West Remediation, and are now delivering Stage 2. This is our sixth project for Port of Melbourne since 2017.
Swanson Dock West (SDW) is a critical International Container Terminal comprising of a 944 m wharf with three container-handling berths, which were constructed in several stages between the 1960s and 1980s. The existing wharf is of varying forms of construction and some sections are close to or beyond the typical design life of 30 years. As a result, major remediation was needed.
During the Australian resources boom (2004-2014), BHP challenged us to design and construct two new iron export wharves on a fast tracked program to support their rapid growth program (RGP) initiative.
To meet the challenge, while delivering safely and to a high quality, we broke new ground in large-scale marine modularisation, making it central to our construction approach.
At the height of the Australian resources boom (2004-2014), we became the marine partner of choice for Fortescue Metals Group (FMG), as they developed the infrastructure to support their new iron ore export business.
We completed the main berth construction scope for BHP Mitsubishi Alliance's (BMA) SABR Project, using the Early Contractor Involvement process to develop a number of innovations.
SABR, short for 'Shiploader and Berth 2 Replacement', was a brownfields project located within the lease boundaries of BMA's existing Hay Point Coal Terminal near Mackay, Queensland. It included the disassembly and replacement of one of the existing shiploaders and berths to improve materials handling throughput and cyclonic wave immunity.
It's the technical problems and challenges solved behind the scenes by people empowered to think creatively and work collaboratively. It’s the alternative idea or innovation that saves time, reduces cost, makes us safer, and delivers more value.
It might not always be evident when you look at the end product, but it's there, inside every McConnell Dowell project.
On the Granite Island Causeway Project in South Australia our team used the 'hand over hand' construction method to minimise environmental impacts and ensure delivery on time.
The 'hand over hand' method employs three concurrent work fronts:
As the structure advances out into the water it acts as a construction platform for the work crews to build the next stage. Each work front takes a similar duration, ensuring maximum certainty in productivity and schedule.
Analysis was conducted on various construction approaches during the tender phase, including the use of jack-up barges or a temporary bridge structure to facilitate construction. However, the 'hand over hand' method was the only one capable of achieving completion by the target date.
The other benefit of the method is its minimal footprint. Minimising the impact on the sensitive marine environment was a key consideration during the tender and design phases of the project.
The adoption of the method, along with the use of precast prestressed deck units which pushed the span out as far as possible, minimised the number of pile driving operations further reducing the impact on the marine environment.
The design and construction methodology was fit-for-purpose and extremely efficient. It resulted in on time and on budget completion and had a low impact on Victor Harbor's rich marine ecology.
Our marine engineering specialists are always on the lookout for ways to minimise the impact of our works on sensitive environments, and a recent example comes from the New Bridgewater Bridge Project in Tasmania.
The project involves a new 1,300 m long bridge built across the River Derwent. The bridge is being erected from a temporary access platform, which crosses shallow tidal mudflats that have significant environmental, cultural and heritage importance. The temporary access platform allows continuous access for delivery and lifting of segments along the bridge alignment
The initial design for the temporary access platform included piles, but this approach was deemed to have significant environmental, cost and program impacts.
So an alternate and innovative construction methodology was developed by our marine specialists.
While the shallow tidal mudflats prevented the use of floating crane barges, interconnected barges placed on the seabed form the basis of the solution.
Standard (flat-top, 55 m long) barges have been floated into position at high tide, trimmed and ballasted down onto the mud flats. The barges are connected using specifically designed link bridges, allowing movement of equipment over a total length of about 800 m.
The innovative design caters for critical issues such as differential settlement of the very soft muds under cyclic loads; dynamic lifting loads; and load sharing between barges. Specific lift plans have been developed to address key risks during erection.
The linked barges design provides a safe and cost-effective solution while minimising the impact of construction activities on the environmentally sensitive mudflats. After the barges have been removed the mudflats are expected to recover completely. The barges and link bridges can also be re-used on other marine projects, unlike the original piled solution.
On the Granite Island Causeway project in South Australia, our team designed and implemented a "shroud and bubble curtain" to stop marine piling noise from disturbing the Southern Right Whale (SRW) and other marine fauna, such as the Australian sea lion and little penguins.
Prior to the solution being developed and approved, a local whale protection group strongly objected to piling occurring during whale season, which had the potential to impact the project's schedule and budget.
The bubble curtain was designed to reduce the noise levels by scattering, absorption, reflection, and refraction of the sound waves. The curtain design, along with some other piling modifications, gave sufficient confidence for federal approval under the Environment Protection and Biodiversity Conservation Act for piling during the whale season.
We helped revolutionise the design and construction approach for large-scale marine infrastructure on Rio Tinto's Chith Export Facility project in remote Far North Queensland.
The 350m wharf structure was split into seven, first-of-a-kind ‘jacket’ modules (the substructure) and six topside modules. Weighing approximately 680 tonnes each and standing 30m high, the jacket modules, with integrated dolphins, reduced the number of permanent wharf piles required from 100 to just 28, minimising environmental impact to marine life – a core focus for the Chith Export Facility team.
The wharf topside modules, placed on the jackets, ranged from 600 to 1400 tonnes and were fabricated complete with all services, conveyors, concrete roadways and access walkways.
In true ‘plug and play’ fashion, the modules were delivered and installed by a heavy-lift ship in a safe, clean and efficient operation.
The project, completed in just 10 months, was awarded the Australian Construction Achievement Award by Engineers Australia and the Brunel Medal by the Institute of Civil Engineers (UK).
In marine environments, where the margin for error is razor-thin, temporary works aren’t mere enablers—they’re foundational to safe, efficient delivery.
Take the Swanson Dock upgrade at the Port of Melbourne. Our temporary works team engineered an innovative fender access platform, earning the a WorkSafe Victoria award for “Best Solution to a Specific Workplace Health and Safety Issue”
Here’s what set it apart:
Why Temporary Works Matter
Prioritising safety at early design stages – Proactively engineering safe access platforms significantly diminishes risk in live marine settings.
Driving productivity through better access – Easier, safer access means faster cycle times and fewer quay-side delays.
Enabling precise engineering works – Demolition, rebar placement, and spraying all demand stable, safe working environments—temporary works deliver just that.
Promoting sustainability and reuse – Modular, reusable temporary works not only save time but also cut embodied carbon across projects.
By spotlighting temporary works as a core part of project delivery—not an afterthought—we’re reshaping how marine construction tackles safety, efficiency, and sustainability.
This helps them identify and address potential issues at the earliest stages of project development, effectively eliminating issues at their genesis leading to lower costs and delays once we start on site.
On site, we use digital tools like drones for surveying, and GPS tracked plant to monitor and improve safety and efficiency.
Our approach is clearly articulated in our Sustainability Policy.
We're about action not just aspiration. Our ambitious but achievable {tip title="Carbon Reduction Roadmap" content="
"} carbon reduction road-map {/tip} will see us be operationally net zero by 2030, with 44 initiatives that are being progressively rolled out across the company. Last year we reduced our carbon emissions by 442 tonnes through the use of solar technologies alone, and diverted almost two million tonnes of waste from landfill.
Our vision is for the construction industry and the communities in which we work to develop stronger and deeper relationships between Aboriginal and Torres Strait Islander peoples and non-Indigenous peoples for the benefit of all Australians.
Together, we strive to achieve a shared future that is inclusive and equitable for all Australians.
Thank you for taking an interest in McConnell Dowell's skills, capabilities and approach. Additional information is available on our website, including additional project case studies.
Contact us through the link(s) at the bottom for advice or assistance with your project.
Jan Matthé
Group Technical Director - Ports & Coastal
M: +65 9030 0989
jan.matthe@mcdgroup.com LinkedIn